If a problem occurs in a system 6 months after it completely goes live, what will be the approach for fixing that problem on very urgent basis? A. Do not involve testers B. Just go for retest C. Always go for a full regression test D. Go for a retest and then use risk assessment to decide a reasonable subset of the regression test suit that will be executed. Answer Workspace Report Discuss Answer with explanation Answer: Option D Explanation Go for a retest and then use risk assessment to decide a reasonable subset of the regression test suit that will be executed. Workspace